Technical advice
Asbestos MMVF Lead and PCB Remediation

Asbestos remediation – Former EDF Port Ouest power plant, Réunion

Project description

Asbestos remediation at the site of the former EDF Port Ouest power plant on the island of Réunion, divided into several operational phases. During the work, contaminated concrete debris, coatings and insulating materials were treated by creating dynamic confinement under negative pressure and using controlled air-exchange systems.

The initial phase involved safety operations prior to the main remediation, while the second phase was dedicated to treating contaminated plaster present in the basements of the buildings already subject to intervention.

Client:
EDF
Site:
Former EDF Port Ouest power plant
Year:
First phase: 2020
Second phase: 2023 – ongoing

crossmenuchevron-down
This site is registered on wpml.org as a development site. Switch to a production site key to remove this banner.